Posted on: August 24, 2016

QAC Court House Ground Breaking Ceremony

Ct. House Ground Breaking websize panoramic.jpg

A Ground Breaking Ceremony was held Aug. 23rd for the new QAC Circuit Courthouse on Commerce St. in Centreville.

Queen Anne’s County New Circuit Courthouse
Project Physical Characteristics
The new circuit courthouse facility will be approximately 42,000 square feet on 2 levels located on an existing 1-acre site within the town of Centreville. Site amenities will include landscaping, hardscaping, site access, storm water management and all utilities and communication infrastructure including a fiber optic backbone. One of the most unique features of the new courthouse, it will be the first newly constructed Maryland Electronic Courthouse (MDEC) hosting full electronic technology to be built in the state of Maryland.
The building structure will be comprised of reinforced concrete, structural steel beams and columns and block walls with brick and limestone façade. The brick and limestone exterior was selected, by the Courthouse Citizens Committee, from 18 different options presented by the Architect. Texture and color for the brick and limestone façade was selected to complement and favor the existing surrounding buildings. The main entrance and front elevation are designed with a blend of brick and limestone to replicate the historic and charming character of the existing courthouse and the town of Centreville. The eagle emblem above the main entrance doors is artfully etched to exactly match the eagle emblem on the existing circuit courthouse building.
The grounds of the new courthouse will be elegantly landscaped together with hardscape features including a fountain, benches and brick walkways.
The new circuit courthouse will accommodate two full service courtrooms, one Masters Courtroom, a Family Service Center, and two detention areas with comprehensive security measures. Both the building and grounds will be in full compliance with ADA requirements and regulations.
In addition, the mechanical and electrical systems are designed with diligent consideration to energy efficiency and environmental sensitivity.
This new courthouse is replacing the existing courthouse that was built during the presidency of George Washington between 1792 and 1794, some 224 years ago.
Project Cost and Schedule
Construction Contract Value: $19,395,694.00
Architect: Beyer Blinder Belle
Contractor: Mullan Contracting Company
Contract Award Date: June 22nd, 2016
Notice to Proceed (NTP) issued: August 1st, 2016
Project Duration: 640 calendar days for substantial completion.
Substantial Completion: May 2nd, 2018
Fully Functional: Late Fall 2018

Facebook Twitter Google Plus Email

Other News in County Commissioners

fitch-cut-rating.jpg

QAC Earns AAA Bond Rating Saving Millions

Posted on: February 28, 2017
Job Openings with QAC Government.jpg

Current QA County Job Openings!

Posted on: February 17, 2017
IHOP coming to KI websize.jpg

IHOP Coming to Kent Island Late Spring

Posted on: February 9, 2017
BAAR Training Session on the SKI Sewer Project websize.jpg

Realtors Attend SKI Training Sessions

Posted on: February 8, 2017

Queen Anne's County Detention Center

Posted on: February 7, 2017
STEP.jpg

Southern Kent Island Sewer - SKI Update

Posted on: January 18, 2017
enterprise zone.JPG

QAC's first Enterprise Zone

Posted on: January 13, 2017
legislative delegation and Maryland department of transportation  Websize.jpg

Commissioners Planning Ahead for 2017

Posted on: November 1, 2016
Open Data.JPG

Open Gov't = Open Data!

Posted on: August 19, 2016
county ride.jpg

QAC County Ride - Available to All

Posted on: July 7, 2016

Have You Seen These Missing Children?

Posted on: October 7, 2015